... the order from the sales office to the sales headquarters, where they have other orders to process, and then sending the information back to the sales office, confirming that the land is sold. This activity must be carried out with activity B (below). Activity B - Design house * No. of workers required - 4 * Duration - 4 days * Precedence - N/A This is because 4 people are required to each plan and draw their own designs of the house. Then they decide which design is the best out of all of the designs. This takes place over 3 days. The final design is drawn carefully on the final day of the activity. This activity must be carried out with activity A (above). Activity C - Seek planning permission * No. of workers required - 1 * Duration - 3 days * Precedence - A and B This is because 1 person is required to present the final ...